The Government of Montserrat through the Ministry of Communication and Works on Friday, May 17, 2019, conducted the Montserrat Port Development Project Launch which has been seriously undertaken when Premier Romeo announced in February last year, that the funds had been sourced for the project.
The event was hosted at the Montserrat Port Authority – Ferry Terminal Building, with an overflow of persons who were outside of the small available space, but with the apparent intention to afford guests the opportunity to tour the site and to ask pertinent questions, especially that there is not yet a design for the actual port.
Port Authority manager Joseph O’Garro chaired the proceedings which began with the singing of the Territorial song and a prayer led by Fr. Carlisle Vyphius of the Anglican church.
Following, were welcome and opening remarks by the port

Mr. O’Garro briefly in his opening and welcome outlined what most or all of the remarks noted, that the project will provide safe, secure and modern port facility for Montserrat, that will provide critical access and reduce down-time especially in times of poor weather.
He, again like others, in addressing the down time noted that about 12% of the vessels calling at Little Bay had not come into, or leave or port.


The Governor said about the project. “It works with the grain of our small island community and it sort of aligns with the niche nature of our economy,” preceding that with the observation. “Size is not everything, quality and balance are key – it matches the scale of little Montserrat – we aren’t going to get and we don’t want almost 4000 berth cruise ships, hopefully smaller ones – we can host graciously…
CDB’s Andrew Dupigny, who has been with the project from early 2017, in his remarks, noted that, “…On completion it is expected that the new facility will provide direct and positive impact on the economy with the potential that would increase employment, improved productivity and overall improvements in the business environment.

Sounding like coming straight out of a business case, he continued to say: “Over the long term the provision of a reliable access and connectivity to the island, the movement of people goods and services would increase its creativity potential which would ultimately positively impact growth – improve the efficiency effectiveness and resilience of the port facility to provide safety and accessibility.” –
When we say that this project goes way, 12 years, further than the Premier would later recall, Dupigny noted “This actually dovetails very well with the government of Montserrat’s ongoing activities to restore access and connectivity to the island,” which he said, “…was articulated in the Hon Premiers presentation of the budget address in 2017 when he declared ‘access is perhaps our single biggest challenge to growth.’”
He connected this to: “CDB’s strategic plan for the period 2015 to 19 similarly recognises, the positive relationship between infrastructure economic growth and poverty reduction.”
He offered, “Good transportation is one of the main elements that supports national development. A Key success of any project especially a project such as this which will impact every community across Montserrat is the participation of stakeholders.”
“We are therefore extremely pleased to see the enthusiasm evidenced by your numbers here this morning as well as a high level of participation in the workshop that took place over the past few days.”
This was a workshop that this long-standing stakeholder in all Montserrat progress media house was excluded and knew nothing about. Such could very well be to the detriment to any project, except for dishonest follow-ups which in the end will as we say be detrimental to Montserrat.
Minister Lewis was firm in his presentation as he set out the history of loss and difficulties with a port that far than less served the required needs of Montserrat, but finally, “a solution.”
He spoke to how, “with unreliable sea access for the last 23 years Montserrat lost opportunities for economic growth, our country’s people suffered other losses, including vessels running aground and the destruction of cargo vessels; loss of fishing vessels and yachts unable to come into port; cost of goods have increased after additional charges were placed on shipping given the uncertainty of docking on arrival in Montserrat and having to wait, perhaps even leave before returning a second time to off load,” referring to unsuccessful attempts as they try to dock in rough waters, having to return to Antigua – the road to a solution has not been without challenges.
He spoke of the benefits to be gained as the project progresses, as well as the revealing that, “The project will also provide employment for 72-100 workers over 18 months to two years.
With all other requirements in place and September this year, for a design and build contractor will take place, thereafter, the successful company will be mobilizing to start work by the end of the year
Funding for this project, after a £23 million offer by the UK was turned down (technically) in early 2014, came with a £14.4 million grant to GoM from the UK government via the United Kingdom Caribbean Infrastructure Partnership Fund (UKCIF), augmented by another £7 million budgetary support from the European Union.
With the (CDB) making an initial allocation for the project, advised to GoM in July 2016, an application for the grant made in March 2017, the agreement between the Caribbean Development Bank (CDB) and the Government of Montserrat for £14,400,000 was signed by Premier Romeo on Wednesday, April 11, 2018.

The Premier was set to deliver the feature address for the event. He, following what took his Government nearly three years to get to this point, recently accessing the needed additional funds, he was relieved probably more than excited.
“Today, marks one of the first, breakthrough step towards the fulfillment of a twenty four-year old hope for Montserrat; a protected sea port here in the safe zone. Yes, the first safe harbour in Montserrat’s history,” he began.
He continued by recalling as many of the arguments that had no doubt, like Dupigny recalled, made in the business case that had to be presented for the port. He quoted DFID: “The principal barrier to economic growth and development on the island is poor physical access.. . . Without the development of Little Bay and Carr’s Bay, improved access, and reduced costs of doing business, Montserrat will remain uncompetitive in attracting [Foreign Direct Investment].”
So he told an appreciable number of many of whom were invited for the event. “The port development project is therefore one of the strategic keys for unlocking growth and building Montserrat’s future.”
Concurring that this key we will open up the door for local and foreign investment and for self-sustaining, private sector led growth, he added: “It will create jobs during the construction phase, and it will provide more reliable docking for Cruise ships and for cargo vessels.”
Like other speakers he pointed out that “due to rough seas…out of a total of 478 calls, vessels were unable to berth 58 times…one vessel out of every eight had to turn back. “Yes, that is not sustainable. We had to fix the problem,” he said
That’s why a safe harbour “is of vital importance in providing connectivity to the island of Montserrat and for supporting economic activity.”
He reminded of earlier attempts at building a port, that the Government of the day had envisioned a sea port development in Carrs Bay, and it had actually knocked down part of Gun Hill to facilitate the project.
With no design yet in place for the current project, he noted that in the previous case, a design was made and developed, being presented to the public at 60% and 90% points. “But, alas, it was very costly and suitable private sector partners were hard to secure,” but giving no details of the contrasts.
He recalled also a statement made by former Chief Minister John Osborne, deceased, in the aftermath of Hurricane Hugo on July 30, 1990: “With assistance in developing its infrastructure, including a proper airport and a safe harbour, Montserrat could develop a viable economy and opt for independence.”

Before closing his address, the Premier gave an insight as to how the project will move from this launch. “First, through presentations and workshops that have been going on for a few days, we look at preliminary designs, then adjust towards a preferred option. The preferred option will then be fully developed as a technical design, starting in August. Then, once that design is completed and accepted, construction will begin.
He revealed that “Construction will take considerable time, over a year,” with a caution. “However, we must always recognise that we are dealing with the sea, which has its own power, its own ways and its own voice; which can force changes to our proposed schedules.”
He concludes after thanking several key authorities, Minister Lewis, UK govt and other key personel, and then: “Let us see, how we can work together as a people as we put in place one of the foundation stones for building our future.”

The P:S gave a fairly descriptive and comprehensive vote of thanks, praising the Ministry and staff for the work done so far on the project and hosting the morning’s event which ended with people looking at and discussing the site from the concept drawing.
Related: https://www.themontserratreporter.com/planning-to-begin-for-a-breakwater-facility-at-little-bay/
“https://drive.google.com/drive/folders/1-cZXxLq1fMwTeH0q5kA4vBcaQdyCsAbz?usp=sharing
https://www.youtube.com/watch?v=jhkzwryf-2w&feature=youtu.be